Earned Value Management (EVM) measures project performance by comparing the value of work actually completed (Earned Value) against what was planned (Planned Value) and what it cost (Actual Cost). From these it derives schedule and cost variances and performance indices (SPI, CPI).
Its power is forecasting: by mid-project, EVM gives an objective, data-based estimate of final cost and completion date, long before traditional reporting would reveal trouble.
Example. A work package is budgeted at $100,000 over 10 months, so Planned Value at month 4 is $40,000. The work is 30% complete, so Earned Value is $30,000. Actual Cost booked is $36,000. Schedule variance is 30,000 - 40,000 = -$10,000 and SPI is 0.75; cost variance is 30,000 - 36,000 = -$6,000 and CPI is 0.83. The estimate at completion at this cost efficiency is 100,000 / 0.83 = $120,000.
EVM is only as good as the percent-complete rule. Use objective measures (milestones, units completed) for anything over a month long, and 0/100 or 50/50 for short tasks, so progress cannot be claimed by opinion. The EVM guide covers the metrics and the EVMS guide the full system for government contracts.