32
EIA-748 Guidelines
5
Process Areas
$20M+
Threshold
3
Integrated Dimensions

The Problem EVMS Solves

Traditional project management tracks two things independently: how much money has been spent (cost) and where we are on the schedule (time). Neither tells you the critical question: are we getting the work done for the money we are spending?

Consider a program that has spent $50M of its $100M budget and is 12 months into a 24-month schedule. A traditional report says: “50% spent, 50% time elapsed — on track.” But what if only 35% of the work has actually been accomplished? The program is not on track — it is heading for a $43M overrun and a 7-month delay. Without EVMS, this reality is invisible until the money runs out.

EVMS adds a third dimension: earned value — the budgeted cost of the work actually performed. By comparing earned value to both planned value and actual cost, you can detect problems months or years before they become crises.

The Three Fundamental Measurements

MetricOld NameQuestion It AnswersSource
Planned Value (PV)BCWSHow much work should have been done by now?The baseline schedule × budget
Earned Value (EV)BCWPHow much work has actually been accomplished?Objective measurement of completed work
Actual Cost (AC)ACWPHow much have we actually spent?Accounting system

From these three numbers, everything else is derived. The entire EVMS framework — CPI, SPI, EAC, VAC, TCPI — is built on the relationship between PV, EV, and AC. Get these three right and the rest follows.

📊 The Three Measurements in Action Month 12 Status
MetricValueInterpretation
PV (Planned Value)$50MWe planned to have $50M worth of work done by now
EV (Earned Value)$35MWe have actually accomplished $35M worth of work
AC (Actual Cost)$50MWe have spent $50M to do it

Schedule Variance: SV = EV – PV = $35M – $50M = –$15M behind schedule

Cost Variance: CV = EV – AC = $35M – $50M = –$15M over budget

We have accomplished $35M of work but spent $50M doing it (cost overrun), and we should have accomplished $50M by now (schedule delay). Traditional reporting showed “on track.” EVMS reveals the truth.

The 5 Process Areas

AreaGuidelinesPurposeKey Activities
1. Organization1–5Define the work and who does itWBS decomposition, OBS mapping, RAM (Responsibility Assignment Matrix), control account definition
2. Planning, Scheduling & Budgeting6–15Establish the performance measurement baselineSchedule network, time-phased budget, work authorization, baseline establishment
3. Accounting16–21Track actual costs accuratelyCost collection by WBS element, material accounting, indirect rate application
4. Analysis & Management Reports22–27Analyze performance and report to stakeholdersVariance analysis, EAC development, management reporting (CPR/IPMR)
5. Revisions & Maintenance28–32Manage changes to the baselineInternal replanning, baseline change requests, undistributed budget, management reserve

The Control Account: Where EVMS Lives

The control account (CA) is the fundamental building block of EVMS. It is the intersection of the Work Breakdown Structure (what work) and the Organizational Breakdown Structure (who does it). Each control account has:

ElementDefinition
Control Account Manager (CAM)One person responsible for scope, schedule, and budget within this CA
ScopeA defined set of work packages with clear deliverables
ScheduleStart and finish dates for each work package, linked to the IMS
BudgetTime-phased budget (BCWS) distributed across work packages
Earned Value methodHow “percent complete” will be objectively measured

The Control Account Management track covers CAM responsibilities in depth.

💡 EVMS Is Not Just for the Government

While EVMS is mandated on government contracts, the principles work on any project where you need to know: are we on track? The three measurements (PV, EV, AC) and the indices they produce (CPI, SPI) are the most powerful project health indicators ever developed. Commercial aerospace programs, internal capital projects, and even IT programs benefit from earned value thinking — whether or not compliance is required.

🎯 The Bottom Line

EVMS integrates scope, schedule, and cost into a single framework that answers: “Are we getting the work done for the money we are spending?” The 32 EIA-748 guidelines define the system across 5 process areas. The three fundamental measurements (PV, EV, AC) drive every analysis. And the control account is where planning, execution, and measurement converge. Next: Work Breakdown Structure — the foundation that makes everything else possible.

Free forever · Every feature included

Stop reading, start modeling

Model your process flow, run simulations, optimize staffing with TOC math, and test your knowledge with 107 interactive checks — all in one platform.

Open Workbench →

Take this to a room

The running order

For programme staff new to earned value. They should leave able to say what PV, EV and AC are and where a control account sits.

7 beats · 12 min
  1. 1

    The question EVMS answers

    Are we getting the work done for the money we are spending? Cost and schedule alone cannot answer that.

    • Spend against budget tells you nothing about progress.
    • Progress against schedule tells you nothing about cost.
    • EVMS integrates scope, schedule and cost so the two questions become one.

    Ask the room How do we currently know whether a programme is genuinely on track?

  2. 2

    Three measurements, everything else derived

    Planned value, earned value, actual cost. Every index and forecast in EVMS comes from those three.

    • PV: what we planned to have completed by now, in money.
    • EV: what we have actually completed, valued at the plan's rates.
    • AC: what we actually spent to complete it.
  3. 3

    Why it exists

    EVMS is mandated because programmes historically reported green until the money ran out.

    • EIA-748, 32 guidelines, across five process areas.
    • Typically applied above a 20 million dollar threshold.
    • The point is early warning, not a post-mortem.
  4. 4

    The five process areas

    Organisation, planning and budgeting, accounting, analysis, and revisions.

    • Organisation: who is responsible for what, via WBS crossed with OBS.
    • Planning and budgeting: the baseline against which everything is measured.
    • Analysis and revisions: what happens when reality differs from the plan.
  5. 5

    The control account is where it lives

    Everything abstract about EVMS becomes concrete at the control account.

    • It is where a piece of scope, a budget and a named manager meet.
    • Planning, execution and measurement all converge there.
    • If the control accounts are wrong, no amount of analysis above them helps.

    Ask the room Do our control accounts each have one accountable manager?

  6. 6

    It is not only for government work

    The compliance requirement is government. The value is not.

    • The three measurements work on any project where you need to know if you are on track.
    • Commercial aerospace, capital projects and IT programmes all benefit.
    • CPI and SPI are the most useful project health indicators ever developed.
  7. 7

    What to take away

    Three measurements, five process areas, one place they all meet.

    • PV, EV and AC drive every analysis you will ever do here.
    • The 32 guidelines define the system, not the arithmetic.
    • Next question for any programme: is the WBS complete? Everything rests on it.

    Ask the room Which of our programmes could produce PV, EV and AC for last month today?