New to this topic?
We recommend reading these guides first to get the most out of this one:
3
Base Measurements
10+
Derived Metrics
CPI×SPI
Best EAC Predictor
1.0
Target Index

The Complete Metrics Reference

MetricFormulaWhat It Tells YouGood/Bad
PV (Planned Value)From baselineHow much work should be done by nowReference only
EV (Earned Value)% complete × BACHow much work IS done (in budget terms)Higher is better
AC (Actual Cost)From accountingHow much we have spentLower is better
BAC (Budget at Completion)Total baseline budgetHow much the whole job should costReference only
CV (Cost Variance)EV – ACOver or under budgetPositive = under budget
SV (Schedule Variance)EV – PVAhead or behind schedulePositive = ahead
CPI (Cost Performance Index)EV ÷ ACDollars of work per dollar spent>1.0 = under budget
SPI (Schedule Performance Index)EV ÷ PVWork accomplished vs. planned pace>1.0 = ahead
EAC (Estimate at Completion)Multiple formulasWhat the total job will actually costLower is better
ETC (Estimate to Complete)EAC – ACHow much more we need to spendLower is better
VAC (Variance at Completion)BAC – EACExpected overrun/underrun at finishPositive = underrun
TCPI (To-Complete Performance Index)(BAC – EV) ÷ (BAC – AC)Required future CPI to finish on budget>1.0 = must improve

Worked Example: All Metrics

📊 Program Status at Month 18 Complete Metric Set

Program: 36-month duration. BAC = $120M.

At month 18: PV = $65M, EV = $52M, AC = $68M.

MetricCalculationResultInterpretation
CV$52M – $68M–$16M$16M over budget
SV$52M – $65M–$13M$13M behind schedule
CPI$52M ÷ $68M0.765Getting 76.5 cents of work per dollar spent
SPI$52M ÷ $65M0.800Accomplishing 80% of planned work rate
EAC (CPI)$120M ÷ 0.765$156.9MProgram will cost $156.9M if current efficiency continues
ETC$156.9M – $68M$88.9MStill need $88.9M to finish
VAC$120M – $156.9M–$36.9MExpected $36.9M overrun at completion
TCPI($120M – $52M) ÷ ($120M – $68M)1.308Must achieve CPI of 1.31 on remaining work to finish on budget — extremely unlikely

Bottom line: This program is in serious trouble. CPI of 0.765 at 50% completion has never recovered in DoD history. The TCPI of 1.308 means the program would need to become 31% more efficient than budget on all remaining work — effectively impossible without a fundamental scope or approach change.

Earned Value Techniques

The hardest part of EVMS is objectively measuring “percent complete.” Several techniques exist, each appropriate for different work types:

TechniqueHow It WorksBest For
0/1000% until complete, then 100%Short-duration tasks (≤2 months)
50/5050% when started, 100% when completeShort tasks where start is a meaningful milestone
Milestone WeightedAssign % to intermediate milestones (e.g., 25% at PDR, 50% at CDR)Engineering tasks with defined review gates
Percent CompleteSubjective assessment of completionUse sparingly — prone to “90% done syndrome”
Units CompleteUnits delivered ÷ total units plannedRecurring production (aircraft, engines, assemblies)
Level of Effort (LOE)EV = PV (always on plan by definition)Support activities (PM, admin) that cannot be objectively measured. Minimize LOE — it masks performance.

⚠️ The LOE Trap

LOE work always has CPI = 1.0 and SPI = 1.0 by definition — because EV is set equal to PV. If a large portion of your program is LOE, your indices look better than reality. Programs with >30% LOE are effectively hiding their true performance. Push to convert LOE to discrete work packages with objective earned value measurement wherever possible.

🎯 The Bottom Line

Three base measurements (PV, EV, AC) drive the entire EVMS analysis framework. CPI tells you cost efficiency. SPI tells you schedule efficiency. EAC tells you where you are headed. TCPI tells you what miracle you need to get back on budget. The worked example shows how these metrics turn raw numbers into actionable insight — at month 18, this program’s TCPI of 1.31 tells management they cannot finish on budget without a fundamental change. That is the power of EVMS: early warning, not post-mortem. Next: CPI & SPI Analysis — trend analysis and what the indices really mean over time.

🏭
Free Process Modeler
Map your production flow, find bottlenecks & optimize staffing. No login required.
Try It Free →
💾
Save your learning progress PRO
Track quiz scores, earn badges, and pick up where you left off.
Upgrade →
Free forever · No credit card

Stop reading, start modeling

Model your process flow, run simulations, optimize staffing with TOC math, and test your knowledge with 107 interactive checks — all in one platform.

Open Workbench →