New to this topic?
We recommend reading these guides first to get the most out of this one:
1.0
On-Plan Target
±0.10
CPI Stability Range
20%
Prediction Point
0.90
Red Threshold

Cumulative vs. Current-Period Indices

Index TypeFormulaBehaviorUse For
Cumulative CPIΣEV ÷ ΣACStable, smooths out monthly variation, converges over timeEAC prediction, program health assessment, trend direction
Current-Period CPIMonthly EV ÷ Monthly ACVolatile, sensitive to monthly events (large procurements, milestone completions)Detecting recent changes, identifying emerging problems, validating recovery claims
Cumulative SPIΣEV ÷ ΣPVStable but converges to 1.0 at program end (all planned work eventually done)Mid-program schedule assessment. Less useful near program end.
Current-Period SPIMonthly EV ÷ Monthly PVVolatile but reveals current execution rateMonthly performance assessment, recovery tracking

💡 SPI Converges to 1.0 — Use Schedule Variance Instead

At program completion, all planned work is done, so cumulative EV = BAC = cumulative PV, and SPI = 1.0 regardless of whether the program was 2 years late. This makes SPI less useful for schedule assessment in the program’s final third. Use time-based schedule metrics (slip in months, critical path analysis) alongside SPI for schedule health assessment.

The CPI Stability Rule

The most important empirical finding in EVMS research: cumulative CPI stabilizes after the 20% completion point and rarely improves by more than 0.10 thereafter.

📊 CPI Trend Scenario Program Alpha
Month% CompleteCum CPICum SPIAssessment
610%1.050.92Early — CPI looks good but SPI showing schedule pressure. Indices still volatile.
1222%0.940.88At the 20% point. CPI 0.94 = expect final CPI between 0.84–1.04. SPI declining.
1838%0.910.85CPI continuing to decline. Now expect final CPI 0.81–1.01. Trend is negative — not recovering.
2455%0.880.82Red flag. CPI 0.88 at 55% complete = EAC will be ~14% over budget. Recovery is statistically improbable.

Action at month 24: With CPI at 0.88 and declining, the program team should: (1) develop a realistic EAC using multiple methods, (2) identify the root causes of cost overrun (are we inefficient, or was the baseline wrong?), (3) present management with options: rebaseline, descope, or accept the overrun.

Reading the Trend

PatternWhat It MeansAction
Stable CPI > 0.95Program is executing on or near budgetMaintain. Monitor for emerging issues.
CPI declining month-over-monthGetting worse. New cost drivers are emerging or existing ones are growing.Root cause analysis. Variance Analysis Report on largest CA contributors.
CPI stable at 0.85–0.95Program has a structural efficiency problem. Will not self-correct.Management intervention required. Realistic EAC. Corrective action plan with measurable milestones.
CPI < 0.85Severe overrun. Recovery extremely unlikely without scope or baseline change.Formal rebaseline assessment. Scope trade study. Customer notification.
Current CPI improving but cumulative flatRecent performance is better but not enough to move the cumulative needle.Validate improvement is real (not timing). Check if recovery rate is sufficient to change EAC trajectory.
SPI < 1.0 with CPI > 1.0Behind schedule but under budget. May be “buying schedule” with less work than planned.Examine whether under-budget means underperformance. Check if work is being deferred.

Reporting Thresholds

LevelThresholdAction Required
GreenCPI/SPI ≥ 0.95Normal reporting. Monitor trends.
YellowCPI/SPI 0.90–0.95Variance analysis required. Identify root causes. Corrective action plan within 30 days.
RedCPI/SPI < 0.90Formal CAR/VAR. Management review. Customer notification. Recovery plan or rebaseline assessment.

⚠️ Don’t Manage Indices — Manage the Work

A common dysfunction: program teams focus on “improving CPI” by manipulating earned value claims (claiming more % complete than warranted) or deferring cost recognition. This makes the indices look better temporarily but does not change the reality. Manage the work: reduce rework, improve productivity, control scope. The indices will follow.

🎯 The Bottom Line

CPI and SPI are the vital signs of your program. Cumulative CPI stabilizes early and predicts the future: if it is 0.88 at the 20% point, plan for a final CPI of 0.78–0.98. Current-period indices reveal whether you are getting better or worse. Use both together: cumulative for prediction, current-period for trend detection. And remember — the indices are symptoms, not causes. When they signal a problem, the response is root cause analysis and corrective action on the work, not manipulation of the numbers. Next: Variance Analysis & Reporting — turning index signals into actionable root cause narratives.

🏭
Free Process Modeler
Map your production flow, find bottlenecks & optimize staffing. No login required.
Try It Free →
💾
Save your learning progress PRO
Track quiz scores, earn badges, and pick up where you left off.
Upgrade →
Free forever · No credit card

Stop reading, start modeling

Model your process flow, run simulations, optimize staffing with TOC math, and test your knowledge with 107 interactive checks — all in one platform.

Open Workbench →