New to this topic?
We recommend reading these guides first to get the most out of this one:
Internal
CAM Replanning
BCP
Baseline Change
Trace
Full Traceability
OTB
Over-Target Baseline

Types of Baseline Changes

Not all changes to the plan are created equal. EVMS distinguishes between changes that the CAM can make internally and changes that require formal baseline change control. Understanding this distinction is critical — unauthorized changes are EVMS compliance violations, while failing to make necessary changes leads to a baseline that no longer represents the plan.

Change TypeWhat ChangesAuthorizationTraceability
Internal ReplanningWork sequence, resource assignments, budget phasing within the CA. Total CA budget and scope unchanged.CAM authority, PM awarenessDocumented in CA log. Before/after snapshots retained.
Rolling Wave ConversionPlanning packages converted to detailed work packages. No budget or scope change.CAM authorityPlanning package closure and new WP creation logged.
Internal Budget TransferBudget moved between control accounts within the same WBS branch.Baseline Change BoardFormal BCR with from/to CAs, amounts, and justification.
Management Reserve ApplicationMR allocated to a CA for emergent scope. Increases distributed budget, decreases MR.Program ManagerMR log entry with scope description and budget amount.
External Baseline Change (BCP)Contract modification adds or removes scope and budget. Changes CBB and PMB.Contracting Officer + PMContract mod, BCP, BCR tracing new budget to new scope.
Over-Target BaselinePMB reset above CBB. New baseline exceeds contract budget.Customer concurrence + PMReprogramming agreement. Historical data preserved separately.

Internal Replanning Rules

Internal replanning is the CAM’s most frequently used change mechanism. As execution reveals reality, the CAM adjusts the remaining plan to reflect what they now know. This is expected, normal, and necessary. But it has strict boundaries.

✅ Allowed Internal Replanning

  • Resequencing work packages to reflect updated execution priorities
  • Shifting budget between future periods to match revised resource plans
  • Converting planning packages into work packages
  • Splitting a work package into two smaller ones (within the same CA budget)
  • Reassigning resources from one WP to another within the CA
  • Adjusting EV technique if work has not started and PM concurs

❌ Requires Formal Change Control

  • Changing the total budget of the control account (up or down)
  • Moving budget between control accounts
  • Adding scope not currently in the CA
  • Removing scope from the CA
  • Changing past-period BCWS or BCWP
  • Transferring budget from completed WPs to open WPs if it masks overruns

💡 The “Completed Work Package” Rule

Once a work package is complete (100% EV earned and all actuals posted), its budget should not be modified. Moving residual budget from a completed work package to an open one to cover an overrun is a form of “rubber baselining” that masks performance issues. If a completed WP has unspent budget, that variance is real information — it tells you the plan was conservative. If an open WP is overrunning, that is also real information. Do not let the former hide the latter.

The Baseline Change Proposal (BCP) Process

When a contract modification adds new scope, the program must incorporate it into the PMB through a formal process. The BCP documents the scope, budget, and schedule impact and flows them into the baseline.

Contract Modification Received

The contracting officer issues a contract modification authorizing new scope and budget. The new budget enters the system as undistributed budget (UB) or increases the CBB if accompanied by additional funding.

Impact Assessment

Affected CAMs assess the scope impact on their control accounts. They identify what work packages are needed, what resources are required, and how the new scope integrates with existing plans.

BCP Development

Program control develops the BCP documenting: scope description traced to contract language, budget allocation by CA, schedule milestones, and resource requirements. The BCP must balance — total budget allocated must equal the contract modification value.

Baseline Change Board Review

The program’s baseline change board reviews and approves the BCP. This board typically includes the PM, chief engineer, program control lead, and functional managers. The board ensures the change is properly scoped, budgeted, and scheduled.

Implementation

Approved changes are incorporated into the PMB. UB is distributed to control accounts. New work packages are created. The IMS is updated. All changes are logged with before/after values for traceability.

What Triggers a Rebaseline

A rebaseline — fundamentally restructuring the PMB — is a significant action. It should not be done casually, but it should not be avoided when the baseline has lost its value as a measurement standard.

TriggerDescriptionTypical Response
EAC >> CBBForecast total cost significantly exceeds the contract budget with no recovery path.Over-Target Baseline (OTB). Reset PMB to achievable level.
Major Scope RestructureFundamental change in technical approach, WBS restructure, or large scope deletion/addition.Comprehensive replanning. May require customer-approved rebaseline.
Schedule >> Contract DateCompletion date significantly beyond contract requirement with no recovery.Over-Target Schedule (OTS). Reset schedule baseline to achievable dates.
Cumulative Variance DistortionCumulative variances so large that current-period data is meaningless relative to cumulative data.Reprogramming to eliminate historical variances and reset cumulative counters.
Program RestructureOrganizational changes, contractor mergers, or fundamental program redirection.Full rebaseline with customer concurrence. Treat as a new program start.

Traceability Requirements

Every dollar in the PMB must be traceable from the contract through the CBB, through the PMB, to the control account, to the work package. This traceability chain is what makes EVMS auditable and what gives the data credibility.

Traceability ElementFromToDocumentation
Contract to CBBContract priceCBB (price minus fee)Contract, fee structure document
CBB to PMB + MRCBBPMB + Management ReserveCBB reconciliation, MR log
PMB to CAsTotal PMBSum of all CA budgets + UBRAM/budget crosswalk, CA authorization documents
CA to Work PackagesCA total budgetSum of WP + PP budgetsCA plan, WP budgets, PP budgets
Change TraceabilityEach baseline changeBefore/after budget values by CABCR log, BCP documentation, MR log

💡 The Audit Trail

During an IBR or EVMS surveillance review, the auditor will pick a random dollar amount and trace it from the contract to the work package. If any link in the chain is broken — if a budget increase cannot be traced to a contract mod, BCR, or MR allocation — it is a finding. Maintain the trail in real time; reconstructing it after the fact is painful and often impossible.

🎯 The Bottom Line

Change control is the discipline that preserves baseline integrity. Internal replanning keeps the plan current within the CAM’s authority. Formal changes adjust the PMB when scope, budget, or schedule genuinely change. Traceability ensures every dollar can be followed from contract to work package. Know the boundaries, follow the process, and maintain the trail. The baseline is only useful if everyone trusts it, and trust comes from disciplined change control. Next: The CAM Monthly Rhythm — how all of these processes come together in the monthly execution cycle.

🏭
Free Process Modeler
Map your production flow, find bottlenecks & optimize staffing. No login required.
Try It Free →
πŸ’Ύ
Save your learning progress PRO
Track quiz scores, earn badges, and pick up where you left off.
Upgrade →
Free forever · No credit card

Stop reading, start modeling

Model your process flow, run simulations, optimize staffing with TOC math, and test your knowledge with 107 interactive checks — all in one platform.

Open Workbench →