Lead time is the total elapsed clock time for work to move all the way through a process: order to delivery, or raw material to finished good. Critically, it includes queue time and waiting, which usually dwarf actual processing (cycle) time.
Shortening lead time is a primary lean goal because it improves responsiveness, reduces inventory, and exposes problems. Little's Law shows the most reliable lever is reducing WIP.
Example. An order is released to the floor, waits 3 days in a queue at the first operation, is machined in 2 hours, waits 2 days for inspection, is inspected in 20 minutes, waits 4 days for assembly, assembled in 3 hours, and ships. Lead time is just over 9 days; processing time is about 5.3 hours. Doubling machine speed changes the lead time by an hour. Halving the queues saves four days.
Track lead time from the system timestamps you already have: order release to confirmation, or receipt to ship, and plot the distribution rather than the average, because the customer feels the tail. Little's Law explains the queues: at a fixed throughput, lead time falls only when WIP falls. The Little's Law guide works the relationship; the WIP and Little's Law calculator solves for any of the three.