Standard Time

The time a qualified, trained worker should take to complete a task at a normal pace, including allowances.

  • Work Measurement

Standard time is the benchmark time for a task: the observed time, adjusted by a performance rating to a normal pace, plus allowances for fatigue, personal needs, and unavoidable delays. It is the output of a formal time study.

Standard times underpin capacity planning, labor costing, scheduling, line balancing, and incentive systems. They can be derived by stopwatch study, predetermined motion-time systems (e.g., MTM), or work sampling.

Example. An operator is observed over 20 cycles at an average of 2.40 minutes per unit and rated at 110% (working faster than normal pace). Normal time = 2.40 x 1.10 = 2.64 minutes. With a 12% allowance for personal needs, fatigue and delay, standard time = 2.64 x 1.12 = 2.96 minutes per unit. At 440 productive minutes a shift, that is 149 units per operator per shift for capacity planning.

Rating is the contested step, and consistency across the people doing studies matters more than the absolute value. Standard times belong in the routing (SAP, for example, stores them per operation) and need a revision rule: re-study after a method change, or when actuals drift more than an agreed percentage for a quarter. The time studies guide covers rating, allowances and the study form.