Takt Time: Formula, Units and Worked Examples

Takt time is net available time divided by customer demand. The formula, units, and worked examples for a line, a job shop, a warehouse and an office.

12 min read 8 sections Guide 13 of 14, Lean Foundations Updated

Takt timeTakt = net available time ÷ customer demand

Takt time is the pace customer demand sets for your process: net available time divided by the units the customer needs in that time. If a line has 420 minutes to make 210 units, it must finish one unit every 2 minutes. Takt does not say how fast the process runs; it says how fast it must run. This guide gives the formula, the units to use, and worked examples for an assembly line, a job shop, a warehouse and an office. To run your own numbers, use the free takt time calculator; it returns takt in seconds, units per hour and the operators needed.

The takt time formula

PLANAA×POEE84%
OEEOEE = availability × performance × qualityThe OEE guide

Takt time = Net available time ÷ Customer demand

Both terms cover the same period: a shift, a day or a week.

Net available time is the time the process is staffed, minus planned time when it is not meant to produce:

  • Subtract: breaks, lunch, start-of-shift meetings, planned maintenance, planned cleaning.
  • Do not subtract: breakdowns, waiting for material, slow cycles, changeovers that overrun. Those are losses. They make cycle time worse and show up in OEE; taking them out of available time would hide them inside a shorter takt.

Customer demand is the number of units the customer needs in the same period: actual orders or consumption, or a leveled plan. If demand swings a lot from day to day, level it over a week first (see heijunka) and use the leveled daily rate.

The word comes from German, where Takt is the beat or measure in music. It became a production term in German aircraft manufacturing and was later adopted by Toyota.

Units: seconds, minutes, hours or days

Use the unit the people doing the work can see on a clock. A high-volume assembly line posts takt in seconds; a machining cell in minutes; a heavy equipment or aircraft line in hours or days. The arithmetic does not change, only the conversion:

Time studyStandard time = normal time × (1 + allowance)The Time study guide
You haveTo getDo this
Takt in minutesTakt in seconds× 60
Takt in secondsUnits per hour3,600 ÷ takt
Takt in minutesUnits per hour60 ÷ takt
Takt in daysHours per position× net working hours per day

Convert available time to the target unit before dividing. It avoids the most common rounding error: 1.91 minutes looks like "about 2 minutes", but 114.5 seconds and 120 seconds are a 5% difference in staffing.

Worked examples

4 ERP3 MES2 CONTROL1 SENSE0 PROCESS
ISA-95 levelsFive levels stack from sensors at the bottom to the business system at the top; orders go down and results come up

1. An assembly line on two shifts

A line runs two 8-hour shifts. Each shift has 45 minutes of planned breaks and a start-up meeting. The customer needs 1,160 units a day. One unit takes 300 seconds of manual work, summed over all stations.

Net time = 2 × (480 − 45) = 870 min = 52,200 s
Takt time = 52,200 ÷ 1,160 = 45.0 s per unit
Units per hour = 3,600 ÷ 45 = 80
Operators = 300 ÷ 45 = 6.67, rounded up to 7

Seven operators share 300 seconds, about 43 seconds each, leaving roughly 2 seconds per cycle for normal variation. The chart below shows one way to split it.

Seven operators against a 45-second takt 300 seconds of work split over 7 operators: every bar sits under the takt line, with 1 to 4 seconds to spare.

Example 1: 52,200 s ÷ 1,160 units = 45 s takt; 300 s of work ÷ 45 s = 6.67, so 7 operators. Loads 44, 43, 42, 44, 41, 43 and 43 s sum to 300 s.

2. A job shop cell with a product mix

A machining cell makes three part numbers for one customer. Weekly demand is 60 of part A, 40 of B and 20 of C, 120 parts in all. The cell runs one shift, 5 days, with 7.5 net hours a shift. Work content differs: 15 minutes for A, 20 for B and 30 for C.

Net time = 5 × 7.5 h = 37.5 h = 2,250 min a week
Takt time = 2,250 ÷ 120 = 18.75 min per part
Weighted work content = (60 × 15 + 40 × 20 + 20 × 30) ÷ 120 = 2,300 ÷ 120 = 19.2 min per part
Load = 2,300 min of work against 2,250 min available

The average part needs 19.2 minutes against an 18.75-minute takt, so the cell is 50 minutes short every week, even though part A alone fits easily. In a high-mix shop, compare takt with the mix-weighted work content, not with the easiest part. To model shared machines and mix, use the free mixed shop modeler.

3. A warehouse picking operation

A distribution center ships 2,400 order lines a day over two 8-hour shifts, each with 60 minutes of breaks. A pick, including travel, takes 75 seconds per line.

Net time = 2 × (480 − 60) = 840 min = 50,400 s
Takt time = 50,400 ÷ 2,400 = 21 s per order line
Lines per hour = 3,600 ÷ 21 = 171
Pickers on the floor = 75 ÷ 21 = 3.57, rounded up to 4

Check the peak, not just the day. If 60% of lines (1,440) must be picked on first shift to meet the carrier cutoff, first-shift takt is 25,200 s ÷ 1,440 = 17.5 s, and 75 ÷ 17.5 = 4.3, so 5 pickers on first shift. More on the warehouse version in lean warehousing.

4. An office team

An accounts payable team must process 300 invoices a day. The team works 8 hours with 30 minutes of breaks and a 30-minute daily meeting. Each invoice takes 6 minutes of touch time.

Net time = 480 − 30 − 30 = 420 min
Takt time = 420 ÷ 300 = 1.4 min (84 s) per invoice
People = 6 ÷ 1.4 = 4.29, rounded up to 5

Takt makes the office queue visible: if invoices arrive in a morning batch, the team is a day behind by lunchtime even though it is staffed correctly for the day. See lean office for leveling transactional work.

Operators and stations from takt

Takt turns demand into a staffing number:

Yamazumi chartStacked work elements pile up by station; waste blocks drop out and the stacks level to taktThe Yamazumi chart guide

Minimum operators (or stations) = Total work content per unit ÷ Takt time, rounded up

The result is a floor, not a plan. It assumes the work can be split evenly, which it rarely can. Lay the work elements out against takt on a yamazumi chart, move elements until no operator is above takt, and accept that the real number may be one higher. The line balancing guide covers balance efficiency and how much margin to leave, and the line balancing calculator checks a balance you have drawn.

Takt time vs cycle time

CYCLETAKTLEAD
Takt, cycle and lead timeCycle time at or under takt; lead time is the whole waitThe Takt, cycle and lead time guide
Takt timeCycle time
Question it answersHow often must one unit be finished?How long does the process take per unit?
Set byCustomer demand and available timeThe process, its method and its losses
Changes whenDemand or shift pattern changesThe work, the method or the equipment changes
RuleEvery station's cycle time must be at or just below takt

Lead time, the third term people mix up with these two, is how long one unit spends in the whole process; a value stream map puts takt, each step's cycle time and the total lead time on one page. All three, measured on one line, are compared in takt time vs cycle time vs lead time. Glossary entries: takt time, cycle time, lead time.

Common takt time mistakes

PLANNED TIMEBREAKDOWNSETUPSMALL STOPSSLOWSTARTUPREJECTS
Six big lossesBreakdowns, setups, small stops, slow cycles, startup rejects and production rejects each cut the bar down
  1. Mixing periods. Dividing one shift's minutes by a whole day's demand gives a takt that is too short by the number of shifts.
  2. Leaving breaks in. Gross time makes takt look longer than it is, and the line falls behind every day.
  3. Taking breakdowns out. Subtracting expected downtime shortens takt and buries the loss. Keep losses visible in cycle time and OEE.
  4. Using a forecast nobody believes. Use orders, consumption or a leveled plan, and recalculate when it changes.
  5. Treating takt as a target to beat. Running faster than takt builds inventory and unevenness downstream. The goal is to run at takt, steadily.
  6. Balancing to exactly 100%. A station loaded to exactly takt misses on any cycle that runs a little long. Leave margin for normal variation.
  7. Rounding takt to a convenient number. Posting 2 minutes when the math says 1.91 understates demand by about 5%.

Tools for takt work

The free takt time calculator handles one line at a time. To design stations against takt, level the line and plan the future state offline, use Line Designer Pro. To stack each operator's work elements against takt and compare before and after a rebalance, use the Yamazumi Balancer. For takt on aircraft and other long-cycle lines, where takt is measured in days, read takt time in aerospace.

Takt time questions

What is takt time?

Takt time is the pace customer demand sets for production: the time available to finish one unit if you are to make exactly what the customer needs in the time you have. It is calculated, not chosen: net available time divided by demand for the same period.

What is the takt time formula?

Takt time = net available time / customer demand. Net available time is the time the process is staffed minus planned breaks, meetings and planned maintenance. Demand is the number of units needed in that same period.

How do you calculate takt time?

Add up the staffed time in the period, subtract planned non-production time, convert to the unit you want (seconds, minutes, hours), and divide by the demand for the same period. Two 8-hour shifts with 45 minutes of breaks each give 870 minutes; with 1,160 units a day, takt = 52,200 seconds / 1,160 = 45 seconds.

Do you include breaks in takt time?

No. Planned breaks, lunch and meetings are taken out of available time before you divide. Unplanned stops such as breakdowns are not taken out: they are losses, and they belong in cycle time and OEE.

How do you calculate the number of operators from takt time?

Divide the total work content for one unit by takt time and round up. 300 seconds of work at a 45 second takt is 300 / 45 = 6.67, so 7 operators. That is the theoretical minimum; balance the work so no operator is over takt.

Is takt time the same as cycle time?

No. Takt time is the pace demand requires. Cycle time is the pace the process actually runs. Every station needs a cycle time at or just below takt; if a station is above takt the line cannot meet demand in the time available.

Can you use takt time in a job shop or an office?

Yes, for a product family, a cell or a team that handles repeatable work. Where work content varies by job, compare the average work content per unit, weighted by the mix, with takt, or compare total load with available time.