A3 Template: A3 Problem Solving Report
Write one problem on one page, from background to follow-up.
Example loaded: late shipments on the bracket family.
Filled boxes are tinted. Click a box to go to it.
Get the Plant Floor Briefing: one free template like this every 2 weeks
One guide, one free tool, one problem fixed. Every 2 weeks by email. No spam, unsubscribe any time.
How to write an A3
- Write the title as the problem, not the fix. "Late shipments on the bracket family", not "New paint schedule". Name an owner and a mentor or reviewer.
- Fill the left side with data. Background says why it matters now. Current condition shows the gap with numbers and a chart, such as a Pareto of the reasons. The goal is one measurable sentence with a date.
- Go and see, then find the root cause. Watch the process where the problem happens. Use a fishbone diagram for breadth and a 5 Whys for depth, and check the cause against data.
- Tie each countermeasure to a root cause. Every countermeasure should point at a cause on the left. A countermeasure with no cause behind it is a guess.
- Plan who does what by when. Owners, dates, and the risks you can see. Keep it to what fits in the box.
- Follow up against the goal. Name the metric, where it comes from, and the check dates. If the goal is met, make the change the standard; if not, go back to the root cause.
A3 example: late shipments on one product family
A filled A3 from a metal fabrication plant, written by the production engineer who owned the problem. The numbers are worked so you can check them.
| Section | What the A3 says |
|---|---|
| 1. Background | The bracket family is 30% of plant volume. Our largest customer moved us to "yellow" on its scorecard for late deliveries. |
| 2. Current condition | Q2: 412 orders shipped, 66 late, so on-time delivery was (412 − 66) ÷ 412 = 84.0%, down from 96% in Q1. Late reasons: waiting for paint 41 (62%), missing hardware 14 (21%), other 11 (17%). |
| 3. Goal | On-time delivery of 95% or better for 8 weeks in a row by September 30. |
| 4. Root cause | Paint runs one color batch per week to avoid 90-minute color purges, so an order can wait up to five days for its color. The schedule is built to minimize purges, not to meet ship dates. |
| 5. Countermeasures | Run every color every day (a color wheel). Cut the purge from 90 to 30 minutes with a SMED event. Kanban for the hardware kits. |
| 6. Plan | Week 1 SMED event on the paint purge (process engineer). Week 2 daily color wheel trial on day shift (paint lead). Week 3 hardware kanban (materials planner). Risk: four purges a day use 2 hours; the line runs 16 hours and is loaded about 11, so it fits. |
| 7. Follow-up | Weekly on-time delivery from the shipping report, checked at 30, 60 and 90 days. Late-reason Pareto every week until the goal holds for 8 weeks. |
Notice the chain: the Pareto in section 2 points at paint, the root cause in section 4 explains why paint is late, and each countermeasure in section 5 answers a cause. The A3 problem solving guide walks through each section in more depth.
Why this tool matters
An A3 is a way of thinking more than a form. The one-page limit forces you to keep only what matters: if it does not fit, you do not understand it well enough yet. The left side tells the story (what is wrong and why), the right side the solution (what you will do and how you will know it worked). A mentor reviews the logic at each step, which is how the A3 develops problem solvers, not just reports.
Facilitator tip
Do not finish an A3 in one sitting. Fill in sections 1 to 4, then go to the floor and watch the process. Come back and refine. Show your mentor. The A3 is a living document until the follow-up is done.
Frequently asked questions
What are the 7 sections of an A3?
Background, current condition, goal or target, root cause analysis, countermeasures, implementation plan, and follow-up. The first four sit on the left side and tell the story of the problem. The last three sit on the right and say what you will do and how you will know it worked.
What is an A3 report?
A one-page problem-solving report developed at Toyota. It walks from the problem to verified results in a fixed order, so a reader can check the logic in a few minutes and a mentor can coach the thinking behind it.
Why is it called an A3?
After the paper size. ISO A3 is 297 by 420 mm, close to the US 11 by 17 inch tabloid sheet. The one-page limit is the point: if the story does not fit, it is not clear yet.
How is an A3 related to PDCA?
The left side and the countermeasures are Plan, the implementation plan is Do, and the follow-up is Check and Act. An A3 is PDCA written down on one sheet.
Is there an A3 template in Excel or Word?
This template is filled in on the page. Export it as CSV to open in Excel, or print it and save it as a PDF. For a true 11 by 17 or A3 print with a checked one-page fit, the offline A3 Pro does that.
How long does an A3 take?
Days to weeks, not one sitting. Most of the time goes into the current condition and root cause, which need data and time on the floor. The writing itself takes an hour or two.