Schedule adherence measures how closely actual production matched the plan: the right products, in the right quantity, in the right sequence, on time. It is a key daily delivery metric distinct from raw output volume.
High adherence signals a stable, predictable operation; chronic misses point to upstream variability, unrealistic planning, or bottlenecks. It is a staple KPI on tier boards.
Measure it at the level the schedule is written. If the plan is 40 orders for the day in a set sequence, adherence counts only orders completed on the day in the planned sequence: 32 done on the day but 4 of them pulled forward from tomorrow and 3 of today's left behind gives 29 / 40 = 72.5%, not 80%. Counting volume alone rewards running the easy orders first.
Review the misses by cause each day: material short, machine down, labour short, quality hold, plan not achievable. A plant at 60% adherence with "plan not achievable" as the top cause needs a planning fix (capacity, standard times) before a floor fix. The production scheduling guide covers building a plan the floor can hit and the KPIs guide places adherence among the delivery metrics.
Schedule adherence vs schedule attainment. Attainment counts volume: units or orders completed in the period against the plan, in any mix or order. Adherence counts only what was completed as planned, the right item in the right quantity on the right day and in sequence. In the example above, attainment is 32 / 40 = 80% and adherence is 72.5%. Report both: a gap between them means the floor is hitting the count by running work out of plan, which pushes the miss onto the next day or the next operation.