A milk run is a fixed route that delivers or collects small lots of material at several stops on a fixed time cycle, such as every 30 minutes. It replaces a few large deliveries with many small ones.

  • Supply Chain
  • Flow

A milk run is a fixed-route, fixed-time material delivery loop, named after the dairy delivering and collecting bottles. Internally, a water spider follows a timed route delivering parts to line-side and removing finished work; externally, one truck collects small lots from several suppliers.

Milk runs enable frequent, small, leveled deliveries that support JIT and small batch sizes without the cost of many full truckloads.

Example: sizing an in-plant milk run. A tugger serves 6 line-side stops on a 20-minute cycle. Driving the loop takes 8 minutes and each stop takes about 1.5 minutes to drop full bins and pick up empties, so one lap takes 8 + 6 x 1.5 = 17 minutes. That fits inside the 20-minute cycle with 3 minutes of slack for delays. Each delivery must cover one cycle of use: a station that consumes one part every 60 seconds needs 20 parts per drop (20 minutes x 1 part a minute), so a bin of 20 sets the container size. If the lap time grows past the cycle, add a second route or lengthen the cycle and the bin size together.

A milk run beats forklift deliveries when many points each need small, frequent quantities: the route is predictable, line-side stock stays small, and nobody waits for a forklift. It is a poor fit when parts are bulky or demand at each stop is lumpy and hard to predict.