HPU Forecasting
Learning curves, data validation, and hours-per-unit forecasting.
- 6 guides, each free to read
- About 1.5 hours of reading
- 30 knowledge-check questions, with a plan
Knowledge checks, progress and the completion record come with any plan, from $5 a month. See plans
What the track covers
How to forecast labor hours per unit on a low-rate program: the learning curve and what its percentage means, fitting it to aerospace data, cleaning the data, unit versus cumulative average curves, modeling rate breaks and disruptions, and using it in proposals and estimates at completion.
The run, 6 stops. Read a guide to the end and it gets a boot print on this map. Pass its knowledge check and it gets the X.
Every guide in the list is free to read on its own. The track puts them in order and adds a check after each one.
What a plan adds
- A 5-question knowledge check after each guide, with the reasoning shown for every answer
- Guides unlock in order: score 4 of 5 to open the next one
- Progress saved to your email, so you can pick up on another computer
- A completion record with a verification link you can share
- Every other learning track and the advanced knowledge checks
Plans start at $5 a month and include the offline tools in their tier. Compare plans
Who it is for
- Cost estimators and industrial engineers on aerospace and defense programs
- Program control analysts building EACs
- Proposal teams pricing labor hours
How the track works
- Read the guide. It is the same free guide anyone can open.
- Take the 5-question knowledge check at the end of it.
- Score 4 or more to mark the guide done and open the next one. Missed questions show the right answer and why.
- Finish all 6 guides to get the completion record.
Try a sample question
What does an 85% learning curve mean?
- A85% of workers learn the job
- BEach time cumulative production doubles, the unit hours decrease to 85% of the previous doubling point
- CThe process is 85% efficient
- D85% of parts pass inspection
Show the answer
B. An 85% curve: unit 2 takes 85% of unit 1. Unit 4 takes 85% of unit 2. Unit 8 takes 85% of unit 4. The ratio between doublings is constant.
From the check after Learning Curve Theory.
Other learning tracks
- The Process Architect's Blueprint16 guides. Aerospace manufacturing systems, from theory to production ramp.
- Lean Foundations14 guides. From getting started to takt, cycle time and lead time.
- Lean Master Practitioner20 guides. Four modules, from foundations to leadership.
- IE Methods & Tools17 guides. The core industrial engineering toolkit.
- Quality & Measurement7 guides. OEE, SPC, process capability, and measurement systems.
- Equipment & Maintenance5 guides. TPM, autonomous maintenance, and equipment reliability.
- All learning tracks16 tracks, from lean basics to earned value